DOE Seeks to End MOX Plutonium Disposal Program
The Trump Administration requested $220 million next year “to continue the orderly and safe closure of the Mixed Oxide (MOX) Fuel Fabrication Facility.”
The MOX Fuel Fabrication Facility was intended to eliminate excess weapons-grade plutonium by blending it with uranium oxide to produce a “mixed oxide” that is not suitable for nuclear weapons. The Administration proposes instead to pursue a “dilute and dispose” approach.
Termination of the MOX Facility in South Carolina had previously been proposed — but not approved — in budget requests for the last two years, due to mounting costs.
“Construction remains significantly over budget and behind schedule,” the Department of Energy said in a November 2017 report to Congress. “The MOX production objective was not met in 2015 or 2016 and will not be met in 2017.”
“Due to the increasing costs of constructing and operating the MOX facility, both the Department’s analysis and independent analyses of U.S. plutonium disposition strategies have consistently and repeatedly concluded that the MOX fuel strategy is more costly and requires more annual funding than the dilute and dispose approach,” the DOE report said. The report was released by DOE under the Freedom of Information Act.
Though disfavored by the Administration, the MOX program has a champion in South Carolina Senator Lindsay Graham. “I will fight like crazy” to preserve it unless he is convinced that a superior alternative exists, he said at a February 8 hearing of the Senate Armed Services Committee.
Detailed background on the MOX program can be found in Mixed-Oxide Fuel Fabrication Plant and Plutonium Disposition: Management and Policy Issues, Congressional Research Service, December 14, 2017.
The latest proposal to terminate the MOX program was reported in “Aiken County legislators unsurprised by Trump’s anti-MOX budget” by Colin Demarest, Aiken Standard, February 19.
AI’s high-stakes outputs directly shape American economic, industrial, and technological outcomes. They must not be accepted entirely on the basis of institutional faith rather than verifiable evidence.
It is difficult to assess from photos whether the Sentinel missile is longer or wider overall than the Minuteman, but the Sentinel clearly has a thicker second stage, which could potentially contribute to the missile’s extended range.
By mandating data centers that are clean, flexible, efficient, and beneficial, Colorado can bring opportunities to communities and enhance its overall infrastructure.
FAS is eager to see implementation of metascience to measure what works, promote novel and effective research programs such as the work of the NSF X-Labs program, and create policy that enables the AI-enabled scientific enterprise to reach its full potential, safely.