FAS | Nuke | Guide | Iraq | Facility |||| Index | Search |



Tarmiya
Project 411 / al-Safa Factory
Project 946 / Al Hareth Gen. Est.
33°40'07"N 44°23'53"E

The Iraqi nuclear weapons effort, which was directed from the PC-3 headquarters received raw uranium for processing from mines at Ukashat. Seven facilities were promiment in the calutron enrichment program. Four of these facilities, al-Jesira, al-Atheer and al-Rabbiyah and al-Dijjla at Zafaraniyah, had not been identified by American intelligence as being associated with the nuclear weapons program and consequently escaped any significant damage from coalition airstrikes during the Gulf War. The three other facilities -- Tuwaitha, Tarmiya, and al-Fajar -- were previoiusly identified by American intelligence as being associated with the nuclear weapons program and suffered extensive damage during the War. Baghdad was operating approximately 25 calutron units; 20 at Tarmiya where uranium was enriched to 35%, and 5 at Tuwaitha where enrichment levels of approximately 95% were achieved. Another program for the production of uranium under the Petrochemical-3 project used gas centrifuge enrichment, with two facilities at Al Furat and Rashidiya, and a third under construction at Taji.

Tarmiya, located 30 km NW of Baghdad, was the main site for electromagnetic isotope separation (EMIS) program for the enrichment of uranium. The site included both 1200 mm and 600 mm separators. Tarmiya was the site of the 20 calutrons used to enrich uranium to 35%, located in two buildings at the site. This huge facility was designed to house 90 electromagnetic isotope separators and eight such separators were actually placed in operation in September 1990, resulting in the production of around half a kilogram of 4% enriched uranium. [DGSP 1991-9]

The Tarmiya site had no security fence and no visible electrical capacity; only later did inspectors discover that it was powered by a 30-kV underground electrical feed from a 150 MWe substation several kilometers away. Tarmiya was also situated within a large military security zone, thereby needing no additional perimeter security or military defenses at the site. At this same site, the Iraqis built a multimillion-dollar “chemical wash” facility for recovering uranium from refurbished calutron components. This facility was reportedly as sophisticated and clean as any in the West, and triple-filtered so as not to release any trace effluents into the atmosphere that might have led to its detection once it began operation.

Prior to the first IAEA inspection after the Gulf War, the only known nuclear facilities in Iraq were those at the Al Tuwaitha nuclear center, where nuclear material was being safeguarded. No other facilities were declared in the initial Iraqi statements. That the Tarmiya facility housed a substantial piece of the Iraqi nuclear program was only confirmed after the Gulf War in the early summer of 1991, when the movement there of large saucer-like objects (just prior to the first IAEA inspection of the site) led to the positive identification of the Iraqi calutron program. Much of the equipment at this site was disassembled unilaterally by Iraq, and the components hidden from IAEA inspector teams. These pasts were eventually turned over to IAEA personnel and destroyed in place.

As a result of the second IAEA inspection, the Tarmiya industrial centre was revealed as a site for the electromagnetic isotope separation process (EMIS), a facility capable of producing nuclear-weapons-usable material. This was a large site still in the installation stage, although some production units had begun operation and a small quantity of low enriched uranium had been produced. Iraq declared to the first IAEA inspection team that the site was a plant for manufacturing transformers, an implausible claim. When its true nature was established, later inspections showed that extensive deception had taken place, including laying fresh concrete to hide evidence of the machinery that had been installed and walls which had been painted to hide the presence of uranium. [IAEA April 1992 ]

The Tarmiyah large-scale calutron facility was located in Building 33, which was over 100 meters long, which had the capability to support about 100 calutron units. Tarmiyah is also the location of a calutron facility, which would have served as a second-stage "topping off" plant, taking enriched uranium from the first-stage large-scale calutron facilities, and enriching it to weapons-grade. The smaller calutron facility was located in Building 245, and included room for about 20 calutrons. Both buildings were 6 to 18 months away from being operational at the time of the Gulf War.

Sources and Resources



FAS | Nuke | Guide | Iraq | Facility |||| Index | Search |


http://www.fas.org/nuke/guide/iraq/facility/tarmiya.htm

Maintained by Webmaster
Updated Monday, October 09, 2000 7:47:23 PM