FY98 USAF Military Space RDDS

0603853F Evolved Expendable Launch Veh (EELV) (Space)

COST ($ In Thousands) FY 1996 Actual FY 1997 Estimate FY 1998 Estimate FY 1999 Estimate FY 2000 Estimate FY 2001 Estimate FY 2002 Estimate FY 2003 Estimate Cost to Complete Total Cost
0006 EELV Dem/Val 36,894 42,333 63,260 0 0 0 0 0 0 172,533
Quantity of RDT&E Articles 0 0 0 0 0 0 0 0 0 0


(U) A. Mission Description and Budget Item Justification:

The Evolved Expendable Launch Vehicle (EELV) program is a space launch system development program. The purpose of this program is to replace the current fleet of medium to heavy-lift class expendable launch vehicles (Titan II, Delta II, Atlas II, and Titan IV) with a more affordable family of space launch vehicles. With a nonrecurring development cost of $2 billion, EELV is projected to save 25-50 percent over the current fleet of expendable launch vehicles during a 20 year period. Program content includes the development of the system design, demonstrations of key technologies, modifications to industrial capability and launch facilities, and demonstration launches of both medium- and heavy-lift EELV variants. The EELV family of vehicles must be capable of meeting the Government's spacelift needs (DoD, intelligence, and other government missions) through at least 2020, as defined in the National Mission Model. The first operational launch for the Medium-Lift Variant (MLV) is required by FY02 to support satellite block changes and transitions. The first operational capability for the Heavy-Lift Variant (HLV) is required by FY05 to maintain assured access to space following the Titan IV phaseout. This program is in Budget Activity 4, Demonstration and Validation, because it supports risk reduction, demonstration and validation of technologies, and concept verifications leading to lower cost expendable launch vehicles.

(U) Acquisition Strategy:

The EELV concept of a family of launch vehicles emphasizes commonality of hardware and infrastructure and economies of scale to enhance production, operations, and support efficiencies. Cost improvements will be achieved through commonality, consolidation, reduction of supporting infrastructure (launch pads, manufacturing facilities, workforce), and optimization of production and launch operations, processes, and rates. Development contracts will be competitively awarded. Downselect to a single EELV contract/concept is planned at the EMD decision point (third quarter FY98). Production contracts will be sole source to the EELV EMD contractor.

(U) FY 1996
(U) $32,000 Completed four Low Cost Concept Validation (LCCV) contracts culminating in the Dec 96 downselect to two Pre-EMD contracts to continue concept development.
(U) $4,894 Program management and other support costs.
(U) $36,894 Total


(U) FY 1997
(U) $38,854 Awarded two $60M, FFP, Pre-EMD contracts in Dec 96. Pre-EMD contracts will span 17 months.
(U) $3,479 Program management and other support costs.
(U) $42,333 Total


(U) FY 1998
(U) $56,900 Complete two $60 million, firm fixed price, Pre-EMD contracts in May 98.
(U) $6,360 Program management and other support costs.
(U) $0 Downselect to single EMD contractor. EMD begins in June 98 funded under PE 0604853F.
(U) $63,260 Total




(U) B. Program Change Summary ($ in Thousands)

FY 1996 FY 1997 FY 1998 FY 1999
(U) Previous President's Budget 37,147 44,457
(U) Appropriated Value 39,226 44,457
(U) Adjustments to Appropriated Value
a. Congressional General Reductions -916 -1,003
b. Small Business Innovative Research -605 -1,121
c. Omnibus or other above threshold reprogramming -799
d. Below Threshold Reprogramming -12
(U) Adjustments to Budget Years Since FY97 PB +63,260
(U) Current Budget Submit/President's Budget 36,894 42,333 63,260


(U) Change Summary Explanation:

- Funding: The FY96 reductions were for general Congressional reductions and an additional $0.811M reduction to support higher military requirements. FY97 reductions were the result of general Congressional Reductions. FY98 funds were transferred from PE 0604853F (EELV EMD) to reflect the approved schedule for the pre-EMD phase. The pre-EMD phase will run from December 1996 to May 1998. The change is required to implement the approved acquisition strategy as documented in the Single Acquisition Management Plan (SAMP).

- Schedule: Not Applicable.

- Technical: Not Applicable.

(U) C. Other Program Funding Summary ($ in Thousands)
FY 1996 FY 1997 FY 1998 FY 1999 FY 2000 FY 2001 FY 2002 FY 2003 To Comp Total
(U) National User (non-AF budget) 72,300 18,600 7,100 0 98,000
(U) Missile Procurement, AF (PE 030593F) 245,428 285,471 171,951 303,782 Cont. Cont.
Related RDT&E
(U) EELV EMD (PE 0604853F) 28,376 293,950 324,891 232,991 256,797 419,280 162,200 1,718,485
(U) EELV (PE 0305953F) 3,383 3,480 3,577 2,398 795 Cont. Cont.
(U) Medium Launch Vehicles (PE 0305119F)
(U) Titan Space Launch Vehicles (PE 0305144F)


(U) D. Schedule Profile
FY 1996 FY 1997 FY 1998 FY 1999
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
LCCV Module
(U) Tailored Preliminary Design Review X
(U) DAB X
(U) Downselect to two contracts X
Pre-EMD Module
(U) Pre-EMD contract awards X
(U) Downselect Design Review X
(U) EMD DAB X
(U) Downselect to single EMD contract/concept X


(U) A. Project Cost Breakdown ($ in Thousands)
FY 1996 FY 1997 FY 1998 FY 1999
(U) Concept Development Contracts 32,000 38,854 56,900 0
(U) Program management and other support costs 4,894 3,479 6,360 0
(U) Total 36,894 42,333 63,260 0


(U) B. Budget Acquisition History and Planning Information ($ in Thousands)*

* Does not include ARPA FY94 funding of $9,800 and National User funds: FY96 - $72,300, FY97 - $18,600, FY98 - $7,100. Information represents Air Force funding

Performing Organizations:
Contractor or Government Performing

Activity

Contract Method/Type or Funding

Vehicle



Award or Obligation Date


Performing Activity EAC


Project Office

EAC



Total

Prior to

FY 1996





Budget

FY 1996





Budget

FY 1997





Budget

FY 1998





Budget

FY 1999





Budget to Complete




Total Program
Product Development Organizations
Alliant Tech C/FFP (LCCV) Aug 95 13,000 13,000 5,000 8,000 0 0 0 0 13,000
Boeing C/FFP (LCCV) Aug 95 13,000 13,000 5,000 8,000 0 0 0 0 13,000
Lockheed Martin C/FFP (LCCV) Aug 95 13,000 13,000 5,000 8,000 0 0 0 0 13,000
McDonnell Douglas C/FFP (LCCV) Aug 95 13,000 13,000 5,000 8,000 0 0 0 0 13,000
Lockheed Martin C/FFP (Pre-EMD) Dec 96 47,877 47,877 0 0 19,427 28,450 0 0 47,877
McDonnell Douglas C/FFP (Pre-EMD) Dec 96 47,877 47,877 0 0 19,427 28,450 0 0 47,877


Support and Management Organizations
SPO Mission Spt Various Various N/A N/A 852 2,069 2,127 1,676 0 0 6,724
FFRDC CPAF FY95 N/A N/A 1,329 1,803 255 3,833 0 0 7,220
Ranges Various Various N/A N/A 7,255 211 226 110 0 0 7,802
Other Cntr Spt Various Various N/A N/A 610 811 871 741 0 0 3,033


Test and Evaluation Organizations
Not Applicable 0 0 0 0 0 0 0


(U) B. Budget Acquisition History and Planning Information Continued ($ in Thousands)

Government Furnished Property: Not Applicable

Subtotal Product Development 20,000 32,000 38,854 56,900 0 0 147,754
Subtotal Support and Management 10,046 4,894 3,479 6,360 0 0 24,779
Subtotal Test and Evaluation 0 0 0 0 0 0 0
Total Project 30,046 36,894 42,333 63,260 0 0 172,533






THIS PAGE INTENTIONALLY LEFT BLANK