FY98 USAF Military Space RDDS

0305953F Evolved Expendable Launch Vehicle(Space)

COST ($ In Thousands) FY 1996 Actual FY 1997 Estimate FY 1998 Estimate FY 1999 Estimate FY 2000 Estimate FY 2001 Estimate FY 2002 Estimate FY 2003 Estimate Cost to Complete Total Cost
624A Medium Launch Vehicles 0 0 0 3,383 3,480 3,577 2,398 795 Continuing Continuing
Quantity of RDT&E Articles 0 0 0 0 0 0 0 0 0 0


(U) A. Mission Description and Budget Item Justification:

The Evolved Expendable Launch Vehicle (EELV) program is a space launch system development program. The purpose of this program is to replace the current fleet of medium to heavy-lift class expendable launch vehicles (Titan II, Delta II, Atlas II, and Titan IV) with a more affordable family of space launch vehicles. With a nonrecurring development cost of $2 billion, EELV is projected to save 25-50 percent over the current fleet of expendable launch vehicles during a 20 year period. Program content includes the development of the system design, demonstrations of key technologies, modifications to industrial capability and launch facilities, and demonstration launches of both medium and heavy-lift EELV variants. The EELV family of vehicles must be capable of meeting the Government's spacelift needs (DoD, intelligence, and other government missions) through at least 2020, as defined in the National Mission Model. The first operational launch for the Medium-Lift Variant (MLV) is required by FY02 to support satellite block changes and transitions. The first operational capability for the Heavy-Lift Variant (HLV) is required by FY05 to provide for continued assured access to space following the Titan IV phaseout. The program is in Budget Activity 7 Operational System Support because it supports operational deployment of a system in production.

(U) Acquisition Strategy:

The EELV concept of a family of launch vehicles emphasizes commonality of hardware and infrastructure and economies of scale to enhance production, operations, and support efficiencies. Cost improvements will be achieved through commonality, consolidation, reduction of supporting infrastructure (launch pads, manufacturing facilities, workforce), and optimization of production and launch operations, processes, and rates. Development contracts will be competitively awarded. Downselect to a single EELV contract/concept is planned at the EMD decision point (third quarter FY98). Production contracts will be sole source to the EELV EMD contractor.

(U) FY 1996
(U) $0 Not Applicable. EELV was funded in PE 0603853F in FY 1996.


(U) FY 1997
(U) $0 Not Applicable. EELV was funded in PE 0603853F in FY 1996.




(U) FY 1998
(U) $0 Not Applicable. EELV is funded in PE 0603853F and PE 0604853F in FY 1998.


(U) FY 1999
(U) $3,383 Prepare for EELV Production contracts (to be awarded in FY 2000) and start mission planning and non-recurring integration for initial operational satellites.
(U) $3,383 Total


(U) B. Program Change Summary ($ in Thousands)

FY 1996 FY 1997 FY 1998 FY 1999
(U) Previous President's Budget
(U) Appropriated Value
(U) Adjustments to Appropriated Value
a. Congressional General Reductions
b. Small Business Innovative Research
c. Omnibus or other above threshold reprogramming
d. Below Threshold Reprogramming
(U) Adjustments to Budget Years Since FY97 PB +3,383
(U) Current Budget Submit/President's Budget 3,383


(U) Change Summary Explanation:

- Funding: FY99 funds moved from MLV PE (0305119F) as part of the transition from Atlas and Delta to EELV.

- Schedule: Not Applicable.

- Technical: Not Applicable.



(U) C. Other Program Funding Summary ($ in Thousands)
FY 1996 FY 1997 FY 1998 FY 1999 FY 2000 FY 2001 FY 2002 FY 2003 To Comp Total
(U) Missile Procurement, AF (PE 030593F) 245,428 285,471 171,951 303,782 Cont. Cont.
(U) Missile Procurement, AF (QTY) 5 6 3 5 Cont. Cont.
(U) National User (non-AF budget) 72,300 18,600 7,100 98,000
Related RDT&E:
(U) EELV EMD (PE 0603853F). 36,894 42,333 63,260 0 0 0 0 0 0 172,533
(U) EELV EMD (PE 0604853F). 28,376 293,950 324,891 232,991 256,797 419,280 162,200 1,718,485
(U) Medium Launch Vehicles (PE 0305119F).
(U) Titan Space Launch Vehicles (PE 0305144F).


(U) D. Schedule Profile
FY 1996 FY 1997 FY 1998 FY 1999
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
EMD Module
(U) Defense Acquisition Board X
(U) EMD contract award X
(U) Tailored Critical Design Review completed No Later Than date Dec 98 X
(U) Low Rate Initial Production start planned for 1st quarter FY00
(U) System Test Flight #1 (MLV) planned for FY01
(U) System Test Flight #2 (HLV) planned for FY03


(U) A. Project Cost Breakdown ($ in Thousands)

FY 1996 FY 1997 FY 1998 FY 1999
(U) Non-recurring integration funding 3,383
(U) Total 3,383


(U) B. Budget Acquisition History and Planning Information ($ in Thousands)

TBD