
STATEMENT
OF RONALD O'ROURKE
SPECIALIST
IN NATIONAL DEFENSE
Mr.
Chairman, distinguished members of the subcommittee, thank you for the
opportunity to appear before you once again to discuss issues relating
to the Administration's proposed plans for Navy ship recapitalization.
As requested, my testimony will focus on the following issues:
•
the planned size of the Navy;
•
the planned overall rate of Navy ship procurement and its
relationship to the planned size of the Navy; and
•
planned and potential rates of procurement for certain specific
types of Navy ships.
Each of these issues is discussed below.
The
planned size of the Navy
Over the last year,
Department of the Navy (DoN) leaders have begun to openly call into
question the sufficiency in the longer term of the planned fleet of
about 300 ships recommended by the 1997 Quadrennial Defense Review (QDR).
The year 2000 DoN posture statement presented with the proposed
FY2001 defense budget, for example, states:
The Navy and Marine Corps continue to meet their commitments
primarily by drawing upon forward-deployed, “rotational” forces
rather than requiring additional deployments of units that have just
returned from or are beginning to work up for deployment.
We have been able to do this mainly by demanding more from our
people and equipment. But
this cannot go on indefinitely. As
we approach the next Quadrennial Defense Review (QDR) [in 2001], the
Navy and Marine Corps will make the point that our force levels need to
remain balanced with usage expected in the future security
environment.... Already,
there is growing evidence that our forces are stretched....
The 1997 QDR stated that a fleet of slightly more than 300 ships
was sufficient for near term requirements and was within an acceptable
level of risk. Three years
of high-tempo operations, however, suggest that this amount should be
reviewed in the next QDR.[1]
Within the last year, at least three categories of ships within
the 300-ship plan have emerged as specific candidates for increased
force-level goals – attack submarines, surface combatants, and
amphibious ships.
Attack
submarines
.
Although the 300-ship plan established a tentative goal of
maintaining a force of 50 nuclear-powered attack submarines (SSNs), a
Joint Chiefs of Staff (JCS) study on future required SSN force levels
completed in late 1999 and released in unclassified summary form in
early February 2000 concluded that 55 to 68 SSNs would be required in
2015 and 62 to 76 SSNs would be required in 2025.[2] These force-level benchmarks are broadly consistent with the
force-level benchmark established by a previous JCS study on required
SSN force levels, completed in 1992 and updated in 1993, that calculated
a requirement of 51 to 67 SSNs. The
Department of Defense (DoD), in its amended FY2000-FY2005 Future Years
Defense Plan (FYDP), has in effect endorsed the goal of maintaining a
55-ship SSN force over the near-term by including additional funding in
FY2002-FY2005 for submarine refuelings that will be needed to maintain
the attack submarine fleet at about 55 boats for the next several years.
Surface
combatants
.
Similarly, although the 1997 QDR calls for maintaining a force of
116 surface combatants, a study completed in 1999 by the Navy’s
surface combatant community reportedly calls for increasing the goal to
138 ships.[3] This figure, too, is broadly consistent with the results of
other force-level studies carried out by the surface combatant community
in recent years.
Amphibious
ships
.
Lastly, although the 300-ship plan calls for maintaining a
36-ship amphibious fleet organized into 12 Amphibious Ready Groups (ARGs)
with a combined amphibious lift capacity of 2.5 Marine Expeditionary
Brigades (MEBs), Navy and Marine Corps officials have consistently
reminded others in recent years that the 2.5 MEB amphibious lift goal is
a fiscally constrained figure, and that the full amphibious lift
requirement for many years has been for a force with a combined lift
capacity of 3.0 MEBs.[4] In testimony last year, Marine Corps officials stated that a
3.0-MEB fleet would equate to a 14-ARG, 43-ship amphibious force, with
the 7 additional ships consisting of 2 large-deck (i.e., LHD-type)
amphibious ships, 3 San Antonio (LPD-17) class dock landing ships, and 2
LSD-type dock landing ships.[5]
In addition to these 3
categories of ships, it has often been noted by DoN and DoD officials
and others in recent years that maintaining a continuous or
near-continuous presence of one aircraft carrier in each of the three
major U.S. naval operating areas – the Mediterranean Sea, the Indian
Ocean/Persian Gulf area, and the Western Pacific – would require a
force of 15 carriers rather than the 12-carrier force called for in the
300-ship plan.
Simply adding up some or
all of these potential increases – 5 to 26 additional SSNs, 22
additional surface combatants, 7 additional amphibious ships, and
perhaps 3 additional aircraft carriers – would produce a requirement
for as many as 37 to 58 additional ships beyond the original 300-ship
plan. Such an increase
would produce a required fleet size similar to 346-ship fleet called for
in the 1993 Bottom-Up Review (BUR).
The combined effects of
acting on some or all of these proposals, however, could be even
greater, because increasing one part of the fleet could lead to a
consequent need to increase other parts as well.
In particular, the results of the SSN and surface combatant
force-level studies do not appear dependent on an assumed increase in
other parts of the fleet. Increasing
the number of aircraft carriers, however, could by itself produce an
increase in the requirements for surface combatants (notionally 6 per
carrier group) or SSNs (notionally 2 per carrier group).
Increasing the number of ARGs could by itself similarly increase
the surface combatant requirement by a few or several ships.
And increasing the number of carrier battle groups or ARGs could
increase the required number of combat logistic force ships.
As a consequence, acting on most or all of these proposals might
result, at least in theory, in a requirement for a fleet of more than
360 ships.
As discussed in previous
CRS reports and testimony, whether a Navy of a given size will be able
to perform its stated missions will depend on how technological
developments affect the capabilities of U.S. Navy ships, aircraft,
weapons, and other equipment, and on how the international security
environment develops over the next quarter-century. In assessing potential requirements for U.S. naval forces, it
can be noted that some observers believe that the United States during
this period might be confronted with a larger and more modern Chinese
navy, or a rejuvenated Russian navy, or significantly improved maritime
military capabilities (including so-called area-denial or anti-access
capabilities) in other countries, such as Iran.
The Navy during this period could be called on, as it sometimes
is today, to respond to multiple simultaneous or near-simultaneous
contingencies of various kinds in different regions.
Overall
rate of ship procurement and size of the Navy
The overall rate of Navy
ship procurement and its relationship to the planned size of the Navy
has been a concern in Congress since the mid-1990s.
CRS has previously examined the issue in a 1996 report,[6]
a 1997 report,[7]
and 1997 and 1999 testimony.[8] This testimony updates the analysis to take into account the
Administration's proposed FY2001 defense budget and amended
FY2000-FY2005 ship-procurement plan.
Shorter
term vs. longer term
.
Assuming the roughly 300-ship goal remains in place for now, the
challenge in maintaining a fleet of this size, as discussed in previous
reports and testimony, will occur not in the shorter run (i.e., between
now and about 2010), but in the longer run (i.e., after 2010, and
particularly after 2020). As
a result of the significant downsizing of the fleet during the 1990s,
the Navy today is composed to a large degree of relatively young ships,
and a fleet of about 300 ships consequently can be maintained in the
shorter run with a relatively low ship procurement rate.
After 2010, and particularly after 2020, however, the relatively
large numbers of ships procured in the 1970s and 1980s will reach
retirement age. If ships
are not procured in numbers sufficient to offset these retirements, then
total fleet size at that point will drop below 300 ships.
Steady-state
replacement rate
.
In previous reports and testimony dating back several years, CRS
has focused on the concept of the steady-state replacement rate as a
tool for understanding the relationship between planned force structure
and required procurement rates for ships and other types of military
equipment. Over the last
couple of years, and particularly in presenting its proposed FY2001
defense budget and amended FY2000-FY2005 FYDP, the Administration has
begun to similarly focus on this concept.
As shown in Table 1 below,
the current force-level plan for the Navy, including the
Administration’s amended nearer-term SSN goal of 55 boats, includes a
total of 308 ships. This
planned force has a weighted average service life of about 35 years
(using mid-point values for ship types whose service lives are expressed
as ranges) and a corresponding steady-state procurement rate of about
8.7 ships per year.[9]
Table 1. Navy
ship force-level goals, service lives,
and
steady-state procurement rates
|
Ship
type |
No.
of ships |
Service
life in years (low/mid/high) |
Steady-state procurement
rate (based on low/mid/high service life) |
|
|
|
|
|
Submarines: |
69 |
|
2.00 |
|
|
|
|
|
Ballistic
missile |
14a |
42b |
0.33 |
|
|
|
|
|
Attack |
55 |
33 |
1.67 |
|
|
|
|
|
Aircraft
carriers |
12 |
50c |
0.24 |
|
|
|
|
|
Surface
combatants: |
116d |
|
3.66 |
3.38 |
3.15 |
|
|
|
Cruisers/destroyers |
86d |
35 |
37.5 |
40 |
2.46 |
2.29 |
2.15 |
|
Frigates |
30d |
25 |
27.5 |
30 |
1.20 |
1.09 |
1.00 |
|
Amphibious
ships: |
36e |
|
1.03 |
|
|
|
|
|
Large-deck
(LHA/LHD) |
12 |
35 |
0.34 |
|
|
|
|
|
Other
(LSD/LPD) |
24 |
35 |
0.69 |
|
|
|
|
|
Mine
warfare ships |
16f |
30 |
0.53 |
|
|
|
|
|
Other/auxiliary: |
59 |
|
1.79 |
1.52 |
1.34 |
|
|
|
Command
ships |
4 |
35 |
0.11 |
|
|
|
|
|
Combat
logistic ships |
34 |
35 |
40 |
45 |
0.97 |
0.85 |
0.76 |
|
Support
ships |
21 |
30 |
37.5 |
45 |
0.70 |
0.56 |
0.53 |
|
TOTAL |
308 |
|
9.24g |
8.71g |
8.34g |
|
|
|
Implied
weighted average service life |
|
|
33.3 |
35.4 |
36.9 |
|
|
Source: Prepared by CRS based on U.S. navy data.
Totals for steady-state procurement rates may not add due to
rounding.
Notes
a
The current 18-boat SSBN force is to be reduced to 14 boats
consistent with START II force structure set forth in 1994 Nuclear
Posture Review.
b
Life shown is for Ohio (SSBN-726) class Trident submarines with
mid-life nuclear refueling overhaul.
Future SSBNs, if derived from the Virginia (SSN-774) class
design, would likely have a life-of-the-ship core and consequently a
service life closer to the 33-year life of the Virginia class.
c
Life shown includes a mid-life nuclear refueling complex overhaul
(RCOH) extending service life to about 50 years.
d
In the future, the surface combatant force will move toward a
notional mix of 85 Aegis-equipped cruisers and destroyers and 31 DD-21
class land attack destroyers, all with a service life of 35 to 40 years.
The 30 frigates shown include 8 Naval Reserve Force (NRF) ships.
e
In the near term, amphibious force will include 37 to 39
active-duty ships and 2 NRF ships, pending entry into service of LPD-17
class ships, which will permit the 12-ARG, 2.5 MEB lift goal to be met
with a force of 36 amphibious ships.
f
Includes 5 NRF ships.
Administration’s
plan
. The
Administration's amended FYDP, if implemented, would procure a total of
45 new-construction Navy ships over the 6-year period FY2000-FY2005, or
an average of about 7.5 ships per year.
This is a marginal reduction from the Administration’s plan
last year, which would have procured a total of 47 ships, or about 7.8
ships per year. If
maintained over a 35-year period, the amended plan’s average
procurement rate of 7.5 ships per year would result in a fleet of about
263 ships.
The Administration's previous FYDP from two years ago -- the
amended FY1998-FY2003 ship-procurement plan -- would have procured a
total of 37 ships over 6 years, or an average of about 6.2 ships per
year. If maintained over a
35-year period, this average ship procurement rate would result in a
fleet of about 216 ships. Thus, although the Administration’s amended
FYDP represents a marginal reduction from its submission last year, it
is still considerably closer to the steady-state replacement rate for
maintaining a roughly 300-ship Navy than the previous FYDP from two
years ago.
Catch-up
rate to eliminate backlog
. In
assessing ship procurement plans, it is important to compare the
steady-state procurement rate not only to the
planned procurement rate for the next few years, but to the
actual procurement rate in previous years, because deviations between
the steady-state rate and prior-year actual rate can result in an
opportunity or need to adjust the planned procurement rate to a figure
lower or higher than the steady-state rate.
The steady-state procurement rate is an average rate that must be
maintained over the long run. For
a fleet with a weighted average service life of 35 years, an average
rate of 8.7 ships per year must be maintained over a 35-year procurement
period, so that a total of 308 ships are procured during that period.
If there are some years during that 35-year period in which the
procurement rate is higher than 8.7 ships per year, then there can be
other years where the ship procurement rate can be less than 8.7 ships
per year, so that the average rate for the entire 35-year period works
out to 8.7 ships per year. This
is the opportunity the Bush and Clinton administrations encountered in
the early 1990s, when their newly established force-level goals for the
Navy implied steady-state procurement rates substantially lower than the
Cold War-era procurement rates of the 1970s and 1980s.
Conversely, however, if there are some years during the 35-year
period in which the procurement rate is lower than 8.7 ships per year,
then there will need to be other years where the ship procurement rate
must be more than 8.7 ships per year, so that the average rate again
works out to 8.7 ships per year. The
ship procurement rate first fell below 8.7 ships per year in FY1993, and
is programmed to remain below that rate through FY2005.
Given this plan to procure ships at less than the steady-state
procurement rate for the 13-year period FY1993-FY2005, as we move
further away from the early 1990s, examining the situation from this
converse point of view becomes increasingly appropriate.
FY2010 – roughly the year when the last ships funded under the
current FYDP are delivered to the fleet – is within a few years of the
point at which the ships procured in large numbers during the 1980s will
begin to reach their end of their service lives.
If the Administration’s amended ship-procurement plan is
implemented, a total of 83 ships will be procured during the 13-year
period FY1993-FY2005, or an average of about 6.4 ships per year.
Procuring ships at the steady-state replacement rate of about 8.7
ships per year for 13 years would result in a total procurement of about
113 ships. Implementing
current ship-procurement plans will thus create a cumulative 13-year
ship-procurement backlog since FY1993 of 30 ships relative to the
steady-state ship-procurement requirement (113 minus 83).
The amended FY2000-FY2005 FYDP will account for about 7 of the
ships in this backlog, while the preceding 7-year period (FY1993-FY1999)
will account for the other 23 ships.
This 30-ship "deficit" in ship procurement is not
immediately apparent because of the relatively large numbers of ships
built in the 1970s and 1980s, when the ship-procurement rate was well
above 8.7 ships per year. After
2010, and particularly after 2020, however, when the 1970s- and
1980s-era ships begin to retire, this 30-ship backlog, if not by then
redressed, will be unmasked, and the size of the fleet will fall below
308 ships.
Eliminating this 30-ship backlog over the remaining 22 years in a
35-year ship procurement period beginning in FY1993 will increase the
required procurement rate by about 1.4 ships per year above the
steady-state replacement rate. If
an average procurement rate of about 8.7 ships per year is to be
achieved for the entire 35-year period FY1993-FY2027 (that is, if a
total of 308 ships are to be procured in this period), then for the
period FY2006-FY2027 (the remaining 22 years after FY2005) a total of
225 ships (308 less the 83 procured through FY2005) will need to be
procured, or an average of about 10.2 ships per year.[10]
This adjusted post-FY2005 procurement rate of about 10.2 ships
per year can be called the catch-up rate because it would gradually work
off the backlog of deferred ship procurement that has accumulated since
FY1993 and thereby catch up with the total number of procured ships that
would result from maintaining procurement at the steady-state rate.
In recent years, as it became clear that the ship procurement
rate would remain below the steady-state procurement rate for an
extended period of time, CRS analyses have increasingly focused on the
catch-up rate as well as the steady-state procurement rate in examining
the Administration’s proposed ship-procurement plan.
Although the Administration has recently begun to discuss
steady-state procurement rates and acknowledges that backlogs of
deferred procurement relative to these rates have occurred in ships and
other types of equipment, Administration presentations of the defense
budget have not yet begun to place much emphasis on calculating and
discussing the catch-up rates implied by these backlogs.[11]
The next Administration will have an opportunity to reshape Navy
ship-procurement plans, if it desires, by amending the FY2002-FY2007
FYDP that will be submitted early next year by the outgoing
Administration. One option
available to the next Administration would be to reduce the average
catch-up rate by starting the catch-up period before FY2006. For example, by accelerating the start of the catch-up period
to FY2002, the earliest possible year, the next Administration could
reduce the catch-up rate from the 10.2-ships-per-year figure mentioned
above to about 9.8 ships per year.[12]
Mix
of ships in plan
. An additional way to
assess the Administration’s amended FY2000-FY2005 ship-procurement
plan is to examine the mix of ships to be procured in the plan.
Examining the mix can be useful because the various kinds of Navy
ships have widely varying unit procurement costs.
As a consequence, a ship-procurement plan that calls for
procuring ships at a rate equal to (or less than or higher than) the
steady-state procurement rate in terms of total numbers of ships may not
compare that way in terms of the average required amount of procurement
funding associated with a steady-state procurement rate.
The Administration’s amended FY2000-FY2005 ship-procurement
plan, if implemented, would procure 45 ships, or about 86 percent of the
52 or so ships that would be procured under a plan maintaining the
steady-state average of 8.7 ships per year.
The funding in the Administration’s plan for new ship
procurement (which nets out advanced procurement funding provided before
FY2000 for ships procured within the plan, as well as advanced
procurement funding provided within the plan for ships to be procured
after FY2005) averages about $7.9 billion per year.[13] This
compares to an average of roughly $10 billion per year, or an average of
roughly $1.15 billion per ship, that might be needed for procuring new
ships at the steady-state rates shown in Table 1.[14]
Using this $10-billion figure, the Administration’s amended
shipbuilding plan provides an average of roughly 80 percent of the
average annual funding required to procure new ships at a steady-state
rate and a steady-state mix – somewhat less than the 86-percent figure
derived from examining the numbers of ships to be procured.
This appears due principally to submarines and surface
combatants, which are relatively expensive ships that are
under-represented in the plan relative to their steady-state procurement
rates, and auxiliary ships, which are relatively inexpensive ships that
are over-represented in the plan relative to their steady state
procurement rates.
The shortfall in funding, like the shortfall in numbers of ships,
will have an effect on the downstream (i.e., post-FY2005) procurement
requirement. In the future,
procuring ships at the steady-state procurement rate of 8.7 ships per
year (or the post-FY2005 catch-up rate of 10.2 ships per year) might be
more expensive than might be suggested solely by the total number of
ships per year, because the mix of ships at some point would need to
shift to one that included proportionately larger numbers of relatively
expensive submarines and surface combatants, and proportionately smaller
numbers of relatively inexpensive auxiliary ships.
Procuring ships at the steady-state rate of 8.7 ships per year,
in other words, might in some years cost more than $10 billion per year,
while procuring ships at the catch-up rate of 10.2 ships per year might
in some years require more than $11.7 billion per year (the cost to
procure 10.2 ships per year at an average cost of $1.15 billion per
ship).
Procurement
rates for specific ship types
Within the Administration’s overall shipbuilding plan, at least
four ship categories merit individual discussion – attack submarines,
aircraft carriers, surface combatants, and large-deck amphibious ships.
Each of these is discussed below.
Attack
submarines
. The
post-Cold War downturn in procurement began sooner and was
proportionately deeper for attack submarines than for most other kinds
of Navy ships. As a result,
the cumulative ship procurement backlog for SSNs is particularly acute,
and achieving and maintaining planned SSN force levels will be
particularly challenging. This
issue has been a concern in Congress since the mid-1990s, and has been
discussed by CRS in testimony in 1995[15] and 1997;[16] in a 1997 CRS presentation to a Defense Science Board
task force on the submarine of the future, which issued its report in
1998;[17] a 1999 CRS report on attack submarine programs,[18] and 1999 CRS testimony.[19] This
testimony is updated to take into account three key developments that
occurred over the past year.
Three
key developments
.
Extended (33-year life) for 688s/688Is
.
The first development was a determination by the Navy that it
could safely extend the service lives of all its Los Angeles (SSN-688)
and Improved Los Angeles class submarines – all its 688s and 688Is –
by 3 years, to 33 years. This
reduced somewhat the steady-state procurement rate needed to maintain an
SSN force of a given size, and delayed by a couple of years – from the
mid-2020s to the late 2020s – the point at which the size of the SSN
force might bottom out due to rapid retirements of 688Is procured in
large numbers during the 1980s.
JCS SSN force-level study
.
The second key development is the 1999 JCS SSN force-level study
mentioned earlier. This
study had three main conclusions:
•
“that a force structure below 55 SSNs in the 2015 [time frame]
and 62 [SSNs] in the 2025 time frame would leave the CINC’s [the
regional military commanders-in-chief] with insufficient capability to
respond to urgent crucial demands without gapping other requirements of
higher national interest. Additionally,
this force structure [55 SSNs in 2015 and
62 in 2025] would be sufficient to meet the modeled war fighting
requirements;”
•
“that to counter the technologically pacing threat would
require 18 Virginia class SSNs in the 2015 time frame;” and
•
“that 68 SSNs in the 2015 [time frame] and 76 [SSNs] in the
2025 time frame would meet all of the CINCs’ and national intelligence
community’s highest operational and collection requirements.”[20]
Additional
funding for submarine refuelings
.
The third key development was the Administration’s decision to
add $1.1 billion in funding to the shipbuilding plan in the period
FY2002-FY2005 for submarine refuelings beyond those that had already
been programmed.[21] The money is to be used for maintaining additional SSN force
structure by funding either refuelings of 688-class submarines now
scheduled for early retirement, or refuelings and conversions of older
Ohio (SSBN-726) class Trident ballistic missile submarines (SSBNs) into
cruise missile submarines (SSGNs) with an additional capability for
supporting large numbers of special operations forces.
There are currently 7 older 688s that would require refueling to
avoid early retirement and whose refuelings were not funded in last
year’s plan; the $1.1 billion would be roughly enough to refuel 4 of
them.[22] The Navy is also considering the option of converting up to 4
older Trident SSBNs into SSGNs; the $1.1 billion would be roughly enough
to convert 2 of them.[23]
Backlog
in procurement
.
Current plans call for the procurement of a total of 10 SSNs
during the 16-year period FY1990-FY2005 — the final Los Angeles
(SSN-688) class boat (in FY1990), the second and third Seawolf (SSN-21)
class boats (in FY1991 and FY1996), and the first 7 Virginia (SSN-774)
class boats (one each in FY1998, FY1999, and FY2001-FY2005).
This is an average rate of five-eighths of a boat per year for
almost one-half of the SSNs’ 33-year replacement period.
If, during this 16-year period, SSNs were instead procured at the
steady-state replacement rate of 1.67 boats per year, a total of 26 or
27 SSNs would have been procured. Current
plans, if implemented, would thus create an SSN procurement backlog of
16 or 17 boats for the period FY1990-FY2005.[24]
Effect
on force levels after 2015
.
This 16- or 17-boat backlog in procurement, which is equivalent
to about 30 percent of the 55-boat force-level objective, will be masked
between now and about 2015 by the large numbers of SSNs procured during
the 1980s. After about 2015, however, SSNs procured during the 1980s
will reach retirement age and begin to leave service, and the
FY1990-FY2005 "deficit" in SSN procurement, if not by then
redressed, will begin to be unmasked.
The graph on the next page
shows the consequences on the size of the SSN force for the period
2015-2045 of various SSN procurement rates after FY2005, assuming a
33-year life for most existing SSNs.
The graph comes close to being a best-case projection because it
assumes no early retirements of SSNs beyond those that have already
occurred (i.e., the refueling of all 7 688s whose refuelings were not
funded in last year’s plan), as well as the conversion of 4 Trident
SSBNs into SSGNs. This is
an 11-boat addition to the nearer-term SSN force structure, as opposed
to the 4-SSN or 2-SSGN addition that would be funded by the
Administration’s $1.1 billion in additional FY2002-FY2005 funding.
As can be seen in the
graph, by the mid-2020s, most of the SSNs procured in the 1980s and
earlier years will no longer be in service.
As a consequence, unless the post-FY2005 SSN procurement rate is
increased substantially from the 1-per-year rate programmed for
FY2001-FY2005, the size of the SSN force could drop substantially below
55 boats and remain there until well into the 2030s.
[SSN
force-level graph]
Sufficiency
of various potential SSN force levels
.
If the world security environment between now and 2015 and 2025
evolves in a benign direction, then such a reduction in the size of the
SSN force might be acceptable. If
the world security environment evolves in a less benign direction,
however, then such a reduction could have negative implications for U.S.
security. As mentioned earlier, the period after 2015 could feature a
significant military challenge from modernized foreign military forces.
More particularly, this is the period by which some analysts
believe the proliferation of advanced sensors and weapons will make
surface ships highly vulnerable to attack, which in turn might argue in
favor of having a U.S. Navy that included an increased (rather than a
reduced) number of SSNs.
Achieving
and maintaining force-levels set forth in JCS study
.
Table 2 below summarizes potential post-FY2005 SSN procurement
rates (assuming that the current plan to procure 1 SSN per year during
the period FY2001-FY2005 is implemented), and their relationship to the
force-level benchmarks set forth in the JCS SSN force-level study.
Table 2. Post-FY2005
SSN procurement rate and
JCS
SSN study force-level benchmarks
|
SSN pro-curement rate after FY2005 |
Resulting
SSN force levelsa |
|
|
|
|
2015 |
2025 |
|
|
|
Total (with/without
4 Trident SSGNs)b |
Virginia (SSN-774)
class SSNs |
Total (with/without
1 Trident SSGN)b |
|
|
JCS
benchmark: 55
to 68 |
JCS
benchmark: 18 |
JCS
benchmark: 62
to 76 |
|
1.0 per year |
60/56 |
11 |
37/36 |
|
1.5 per year |
62/58 |
13 |
44/43 |
|
2.0 per year |
64/60 |
15 |
51/50 |
|
2.5 per year |
66/62 |
17 |
58/57 |
|
3.0 per year |
68/64 |
19 |
65/64 |
|
3.5 per year |
70/66 |
21 |
72/71 |
|
4.0 per year |
72/68 |
23 |
79/78 |
Source: Prepared by CRS based on U.S. Navy data.
Notes
a
All force levels shown assume funding of all 7 SSN refuelings not
funded in last year’s plan. (This
year’s plan provides for either 4 additional SSN refuelings or 2
Trident SSGN conversions.) These
additional SSN refuelings would affect SSN force levels primarily
between now and about 2018.
b
Assumes 1 converted Trident SSGN enters service each year in
2003, 2004, 2005, and 2006 and remains in service for 20 years.
All 4 would thus be in service in 2015, while 1 would remain in
service in 2025.
Using Table 2 and the force-level graph, the following
conclusions can be drawn:
•
A post-FY2005 SSN procurement rate of 1 boat per year –
a continuation of the rate planned for FY2001-FY2005 – would
result in an SSN force that would slightly exceed the lower end of the
JCS range for the total number of SSNs in 2015 but fall about 40 percent
short of both the JCS benchmark for the number of Virginia-class SSNs in
2015 and the lower end of the JCS range for the total number of SSNs in
2025. This procurement rate
would also result in a force that bottoms out in 2029-2031 at 28 boats
before recovering to a steady-state force-level of 33 boats in 2036.
•
A post-FY2005 SSN procurement rate of about 3 boats per year
would result in an SSN force that would equal the higher end of the JCS
range for the total number of SSNs in 2015, provided that 4 Trident SSGN
conversions are funded. The
force would slightly exceed the JCS benchmark for the number of
Virginia-class SSNs in 2015 and meet the lower end of the JCS range for
the total number of SSNs in 2025. This
procurement rate would also result in a force that bottoms out at 63
boats in 2026-2028.
•
A post-FY2005 SSN procurement rate of about 4 boats per year
would result in an SSN force that would equal the higher end of the JCS
range for the total number of SSNs in 2015, without funding any Trident
SSGN conversions. The force
would exceed the JCS benchmark for the number of Virginia-class SSNs in
2015 by about 28 percent, and slightly exceed the higher end of the JCS
range for the total number of SSNs in 2025.
This procurement rate would also result in a force that bottoms
out at 78 boats in 2026.
The clear implication of
these numbers is that meeting all three of the JCS fore-level benchmarks
– the two nearer-term (2015) benchmarks the one longer-term (2025)
benchmark – would require a post-FY2005 SSN procurement rate of 3 to 4
boats per year. This would
represent a significant change from the situation last year, where a
post-FY2005 SSN procurement rate of 2 boats per year (in conjunction
with the decision to extend the service lives of 688s and 688Is to 33
years) would have been sufficient to maintain a force of at least 50
SSNs through about 2027 (without funding either the refueling of any of
the 7 SSNs scheduled for early retirement or any Trident SSGN
conversions).
Notional
procurement profiles for meeting JCS benchmarks
.
The average SSN procurement rate in FY2006 and later years needed
to meet the JCS benchmarks could be reduced somewhat if the rate in the
current FYDP is modified to increase the procurement rate above 1 boat
per year prior to FY2006.
18
Virginia-class boats in 2015
.
For example, assuming a six-year lag between the year that an SSN
is procured and the year it enters service, achieving the JCS benchmark
of an SSN force with 18 Virginia-class SSNs by 2015 would require a
total of 18 Virginia-class SSNs to be procured through FY2009.
As shown in the table below, including the 2 Virginia-class boats
already procured in FY1998 and FY1999, this could be accomplished either
by holding the procurement rate at 1 boat per year through FY2005 (as
currently planned) and then increasing it to 2.75 boats per year
starting in FY2006, or by increasing it to 2 boats per year starting in
FY2003.
Table 3. Notional
procurement profiles for
funding
18 Virginia-class SSNs through FY2009
(to
achieve 18 Virginia-class SSNs in 2015)
|
Fiscal
year |
|
|
|
|
|
|
|
|
|
|
|
|
98 |
99 |
00 |
01 |
02 |
03 |
04 |
05 |
06 |
07 |
08 |
09 |
|
1 |
1 |
0 |
1 |
1 |
1 |
1 |
1 |
2 |
3 |
3 |
3 |
|
1 |
1 |
0 |
1 |
1 |
2 |
2 |
2 |
2 |
2 |
2 |
2 |
68 SSNs in 2015
.
Similarly, achieving the upper end of the JCS benchmark for the
total number of SSNs in 2015 (68 boats) would require procurement
through FY2009 of a total of 19 Virginia-class SSNs (if all 4 Trident
SSGN conversions are also funded) or 23 Virginia-class SSNs (if no
Trident SSGN conversions are funded).
As shown in the table below, this could be accomplished either by
holding the procurement rate at 1 boat per year through FY2005 and then
increasing it to 3 or 4 boats per year starting in FY2006, or by
increasing it to about 2.1 or 2.5 boats per year starting in FY2002.
Table 4. Notional
procurement profiles for
funding
19 or 23 Virginia-class SSNs through FY2009
(to
achieve 68 total SSNs in 2015 with 4 or 0 Trident SSGNs)
|
Fiscal
year |
|
|
|
|
|
|
|
|
|
|
|
|
98 |
99 |
00 |
01 |
02 |
03 |
04 |
05 |
06 |
07 |
08 |
09 |
|
19
Virginia-class SSNs through FY2009 |
|
|
|
|
|
|
|
|
|
|
|
|
1 |
1 |
0 |
1 |
1 |
1 |
1 |
1 |
3 |
3 |
3 |
3 |
|
1 |
1 |
0 |
1 |
2 |
2 |
2 |
2 |
2 |
2 |
2 |
3 |
|
23
Virginia-class SSNs through FY2009 |
|
|
|
|
|
|
|
|
|
|
|
|
1 |
1 |
0 |
1 |
1 |
1 |
1 |
1 |
4 |
4 |
4 |
4 |
|
1 |
1 |
0 |
1 |
2 |
3 |
2 |
3 |
2 |
3 |
2 |
3 |
|
1 |
1 |
0 |
1 |
2 |
2 |
2 |
2 |
3 |
3 |
3 |
3 |
62
SSNs in 2025
.
Achieving the lower end of the JCS benchmark for the total number
of SSNs in 2025 (62 boats) would require procurement through FY2019 of a
total of 46 Virginia-class SSNs (assuming 1 of the 4 Trident SSGNs still
in service that year) or 47 Virginia-class SSNs (assuming no Trident
SSGNs still in service). As
shown in the table below (which shows profiles for a total of 47
Virginia-class boats), this could be accomplished either by holding the
procurement rate at 1 boat per year through FY2005 and then increasing
it to 2.86 boats per year starting in FY2006, or by increasing it to
about 2.44 boats per year starting in FY2002.
Table 5. Notional
procurement profiles for
funding
47 Virginia-class SSNs through FY2019
(to
achieve 62 total SSNs in 2025 with no Trident SSGNs)
|
Fiscal
year |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
98 |
99 |
00 |
01 |
02 |
03 |
04 |
05 |
06 |
07 |
08 |
09 |
10 |
11 |
12 |
13 |
14 |
15 |
16 |
17 |
18 |
19 |
|
1 |
1 |
0 |
1 |
1 |
1 |
1 |
1 |
2 |
2 |
3 |
3 |
3 |
3 |
3 |
3 |
3 |
3 |
3 |
3 |
3 |
3 |
|
1 |
1 |
0 |
1 |
2 |
2 |
2 |
3 |
2 |
3 |
2 |
3 |
2 |
3 |
2 |
3 |
2 |
3 |
2 |
3 |
2 |
3 |
|
1 |
1 |
0 |
1 |
2 |
2 |
2 |
2 |
2 |
2 |
2 |
2 |
2 |
2 |
3 |
3 |
3 |
3 |
3 |
3 |
3 |
3 |
76 SSNs in 2025
.
Lastly, achieving the higher end of the JCS benchmark for the
total number of SSNs in 2025 (76 boats) would require procurement
through FY2019 of a total of 60 Virginia-class SSNs (assuming 1 of the 4
Trident SSGNs still in service that year) or 61 Virginia-class SSNs
(assuming no Trident SSGNs still in service).
As shown in the table below (which shows profiles for a total of
61 Virginia-class boats), this could be accomplished either by holding
the procurement rate at 1 boat per year through FY2005 and then
increasing it to 3.86 boats per year starting in FY2006, or by
increasing it to about 3.22 boats per year starting in FY2002
Table 6. Notional
procurement profiles for
funding
61 Virginia-class SSNs through FY2019
(to
achieve 76 total SSNs in 2025 with no Trident SSGNs)
|
Fiscal
year |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
98 |
99 |
00 |
01 |
02 |
03 |
04 |
05 |
06 |
07 |
08 |
09 |
10 |
11 |
12 |
13 |
14 |
15 |
16 |
17 |
18 |
19 |
|
1 |
1 |
0 |
1 |
1 |
1 |
1 |
1 |
2 |
4 |
4 |
4 |
4 |
4 |
4 |
4 |
4 |
4 |
4 |
4 |
4 |
4 |
|
1 |
1 |
0 |
1 |
2 |
3 |
3 |
3 |
3 |
4 |
3 |
3 |
4 |
3 |
3 |
4 |
3 |
3 |
4 |
3 |
3 |
4 |
|
1 |
1 |
0 |
1 |
2 |
3 |
3 |
3 |
3 |
3 |
3 |
3 |
3 |
3 |
3 |
3 |
3 |
4 |
4 |
4 |
4 |
4 |
Potential
procurement issues if JCS benchmarks are adopted
. Adopting the benchmarks in
the JCS study as official force-planning goals would pose at least three
potential issues for Congress relating to funding requirements,
industrial base, and acquisition strategy.
Funding requirements
.
At a procurement rate of 1 boat per year, Virginia-class SSNs
currently cost about $1.9 billion to $2.0 billion per boat to procure.
This cost might come down to roughly $1.8 billion per boat at a
procurement rate of 2 boats per year or $1.6 billion to $1.7 billion per
boat at a procurement rate of 3 or 4 boats per year.
Even with these rate-induced reductions in unit procurement cost,
however, achieving and maintaining SSN procurement rates of 2 to 4 SSNs
per year would require significantly more funding per year for SSN
procurement than is currently programmed in the FYDP.
Annual procurement funding requirements could increase from the
current $1.9 billion or $2.0 billion to roughly $3.6 billion (2 boats
per year), $5.1 billion (3 boats per year), or $6.4 billion (4 boats per
year).
Given these potential required funding levels, SSN procurement in
coming years could be a major defense issue for the next Administration
and Congress. Starting with
the Navy’s shipbuilding budget and working outward, achieving such
levels of funding for SSN procurement result in an increase in funding
pressures on other Navy ship-procurement programs (such as aircraft
carriers, surface combatants, amphibious ships, and auxiliary ships),
other Navy procurement programs (such as aircraft, missiles, munitions,
and C4ISR equipment[25]), other Navy program priorities (such as research and
development or operations and maintenance), program priorities in the
other military services, or the overall size of the defense budget.
Industrial base
.
Increasing SSN procurement from a rate of 1 per year to higher
rates (particularly rates of 3 or 4 per year) could pose expansion and
adjustment challenges for a submarine-construction industrial base that
has maintained an average production rate of less than one boat per year
since FY1990. Issues could
arise at both the supplier and shipyard level.
At the supplier level, many firms that manufactured submarine
components exited that line of business or disappeared entirely during
the 1990s as submarine procurement rates fell from the latter-1980s
level of about 4 boats per year to an average of less than 1 per year.
As a result, some key submarine components are now manufactured
by sole sources. These
firms may find it difficult to rapidly increase production rates due to
limitations on facilities or the ability to rapidly hire and train new
workers. And even if a sole
source can adequately expand its operations, the Navy, with only one
supplier for that component, would not have the option of using direct
competition as a means of ensuring best value to the taxpayer in the
manufacturing of that component.
Other potential component suppliers may exist, but these firms
may find it unattractive to enter (or reenter) the business due to
up-front investment requirements, uncertainty over whether the Navy
would be able to maintain higher submarine procurement rates over the
longer run (and thus ensure an adequate return on investment),
regulatory issues involved in doing business with DoD, and the merits of
competing non-defense business opportunities.
Firms that do choose to reenter the business, moreover, would
require time to establish their operations and be certified by the Navy
as quality producers.
At the shipyard level, the two submarine-construction yards –
Electric Boat (EB) and Newport News Shipbuilding (NNS) – may face a
particular challenge in rapidly hiring and training the thousands of
additional workers that would be needed to maintain a production rate of
3 to 4 boats per year, particularly if labor markets remain relatively
tight. Problems in rapidly expanding shipyard work forces were a major
contributor to the difficulties (and consequent delivery delays and cost
overruns) that were experienced in submarine construction in the 1970s
and early 1980s. In
addition to issues relating to expansion of the work force, policymakers
may want to ensure that the two shipyards are not taking or planning to
take any steps with regard to reducing their submarine production
facilities that would be very difficult or expensive to reverse if
needed to support an increased submarine production rate.
These industrial-base issues could be particularly acute if the
SSN procurement rate is increased from the current rate of 1 per year to
a rate of 3 to 4 boats per year in
a relatively short period of time of 1 to 3 years.
Although some of the notional procurement profiles in the tables
above show such rapid increases in the SSN procurement rate, achieving
such a rapid increase could pose significant industrial-base challenges.
Although the boats could legally be procured in the profiles
shown in the tables, submarines procured during the first few years
after the increase in the procurement rate could well take more than six
years to build. A few or
several years could pass before the industrial base overcomes
nearer-term difficulties in expanding the rate of SSN production and the
SSN delivery rate catches up with the SSN procurement rate.
As a consequence, SSN force levels in the first few years after
2012 would be not quite as high as the projections shown in the graph,
which assume a notional 6-year construction time for an SSN.
In addition to a significant chance of delayed deliveries,
pressures placed on the SSN-construction industrial base could also
create a risk of increased SSN procurement costs (due to delays and
lower productivity of newer workers) or even reduced product quality
(due to pressures to meet cost targets and scheduled delivery dates).
Acquisition strategy
.
The current Virginia-class acquisition strategy – in which
boats are produced jointly by EB and NNS, with each yard
receiving about 50 percent of the dollar value of the work, and each
yard performing final assembly of alternate boats – was arrived at in
1997 after 3 years of sometimes contentious debate within Congress and
between Congress and the Administration. This teamed-production strategy
was designed in large part to respond to Congressional desires to keep
both yards involved in submarine construction in the most economical
fashion during an expected period of very low rate SSN production (i.e.,
about 1 boat per year in the near term, increasing later to 1.5 or 2
boats per year).
If it is possible or likely that SSN procurement in the future
will increase to a rate of 3 to 4 boats per year, policymakers may wish
to consider at least two issues relating to the acquisition strategy for
SSNs. The first is whether
to maintain the current teamed-production arrangement between EB and NNS,
or instead return to the previous arrangement in which each yard built
complete submarines.
In assessing this issue, cost would likely be a key criterion.
In 1997, the Navy estimated that for the low SSN procurement
rates then being contemplated, a teamed- production arrangement in the
near term (i.e., for the first several boats in the program) would be
roughly $100 million per boat more expensive than a single-yard
production strategy at EB, but roughly $150 million per boat less
expensive than a two-yard, separate-production strategy at the two
yards.
Whether and how these costs differences would change under higher
SSN procurement rates of 3 to 4 boats per year is not clear.
It is possible, however, that the cost premium associated with
the two-yard, separate-production strategy would decrease, since a large
part of that premium is due to the fixed overhead costs of maintaining
two complete submarine production lines (rather than the current
functional arrangement of 1-plus production line divided between the two
yards, with some overlap in certain areas).
At low rates of SSN procurement, complete SSN production lines at
both yards would not be intensively used, and the fixed overhead costs
of maintaining them would fall heavily on each submarine that is
produced. At higher rates
of procurement, however, complete production lines at both yards would
be used more intensively, and the fixed costs of maintaining them would
fall less heavily on each submarine that is produced.
Returning to a two-yard, separate-production strategy could also
reduce or eliminate some component-transportation and inter-yard
coordination costs associated with the teamed-production strategy.
Policymakers interested in the possibility of returning to a
two-yard, separate-production arrangement for SSNs may wish to ensure
that the yards do not take any steps that would make it very difficult
or expensive to restart or reestablish the parts of their SSN production
lines that may be unused or eliminated during the current period of
teamed production.
If policymakers decide that it would be desirable to return to a
two-yard, separate-production strategy for cost or other reasons, a
second potential question that would arise is whether it would be
further desirable and feasible to resume the use of competition in the
awarding of SSN construction contracts.
Many policymakers believe that competition in defense acquisition
can generate benefits in restraining cost, improving product quality,
encouraging adherence to scheduled delivery dates, and promoting
innovation. In
Congressional debates on SSN procurement strategy in the early to
mid-1990s, one of the arguments offered by some supporters of keeping
both yards involved in submarine construction was that this would
maintain a potential for resuming competition in the awarding of SSN
construction contracts should the SSN procurement rate ever return to
levels high enough to support a competitive approach.
During the early- to mid-1990s debates on SSN procurement, it was
suggested that a procurement rate of 2 or even 1.5 boats per year could
be sufficient to resume competition in the awarding of SSN construction
contracts. (At 1.5 boats
per year, it was suggested, a competition could be held once every 2
years for the 3 boats procured during those 2 years.
Each yard would be guaranteed 1 of those boats, and the two yards
would compete for the third boat.)
Others questioned whether rates this low could sustain a
meaningful competition (i.e., a competition that generated true
bargaining leverage for the government) without putting the two yards
into financially risky situations.
At a procurement rate of 3 to 4 boats per year, however,
maintaining a competition between the two yards in the awarding of SSN
construction contracts would appear more feasible.
In the 1980s, when SSNs were last procured at a rate of 3 or 4
boats per year, the Navy held annual competitions between the two yards
for the contracts to build the boats procured each year.
In the 1990s, when the reduction in the SSN procurement rate led
to a decision to switch to an acquisition strategy that did not employ
competition in the awarding of SSN construction contracts, some
observers questioned in retrospect whether the annual competitions in
the 1980s achieved significant benefits for the government.
They argued that these were competitions in form only because the
uncertainty over the government’s contract-award decisions was tightly
bounded by the production capacity at each yard combined with the
knowledge of how the Navy had divided the previous year’s SSN
construction contracts. Others
argued that the competitions did in fact generate significant bargaining
leverage for the government, these factors notwithstanding.
If policymakers decide that returning to the use of competition
in the awarding of SSN procurement contracts would be desirable, the
other question to address is whether it would be feasible in the wake of
the teamed-production arrangement.
In implementing this strategy, EB and NNS shared many of their
submarine-production trade secrets with one another, so as to ensure
that each part of the submarine would benefit from the combined
production know-how of both yards.
Such production trade secrets – for example, ways of
manufacturing or assembling certain parts of the submarine, or of
managing certain phases of the construction process – can be critical
in gaining a bidding advantage over a rival shipyard in a competition
for construction contracts. Having
revealed these trade secrets to one another, one or both of the two
yards might object strongly to the idea of the government resuming
competition in the awarding of SSN construction contracts, since such a
competition might result in a yard’s own production trade secrets
being used against it in the bidding process by the rival yard.
A yard that believed it shared more valuable trade secrets than
it received from the other yard would likely view a resumption of
competition as fundamentally unfair.
Others, however, could argue that the divulging of these trade
secrets was an unavoidable feature of an acquisition strategy that was
implemented in part to preserve a potential for resuming competition at
some point in the future. They might also argue that the potential unfairness of having
one’s trade secrets used by the other yard will diminish over time as
the design of the Virginia class evolves (due to insertion of new
technologies) and thereby creates opportunities for developing new
production trade secrets for building these modified parts of the boat.
One possible approach would be to let a few or several years pass
between the return to a two-yard, separate-production strategy and the
resumption of competition between the yards, so as to give the yards time
to develop new production processes and practices that can generate
bidding advantages in a subsequent competition.
Aircraft
carriers
. Accommodating
the funding needs of aircraft carrier procurement in the DoN budget has
been an issue for many years. This
is due to three factors – the high unit procurement cost of aircraft
carriers relative to other Navy ships (and all other DoD platforms and
weapons); the relatively infrequent appearance of aircraft carriers in the
budget as a procurement item (their steady-state replacement rate is about
1 ship every 4 years); and a DoD budgeting rule known as the full funding
policy, which requires the full procurement cost of any item funded
through the procurement title of the DoD appropriation act to be provided
in the year in which the item is procured.[26] Together,
these three factors can create a situation in which funding the
procurement of an aircraft carrier can crowd out funding for other Navy
program priorities unless the Navy budget is allowed a one-year increase
above its prevailing level – a so-called budget “spike” – to
accommodate at least some of the carrier’s procurement cost.
As shown in the table below, there is a mixed history in recent
years regarding the use of a DoN budget spike to facilitate aircraft
carrier procurement. The
procurement of aircraft carriers in FY1983 and FY1988 coincided with
apparent DoN budget spikes for those years
that are equivalent to most of the cost of these carriers, while
procurement of carriers in FY1980 and FY1995 do not coincide with such
spikes. (Indeed, overall DoN
budget totals suggest, if anything, a negative budget spike in FY1995.)
Under the Administration’s amended FYDP, the planned procurement
in FY2001 of the next aircraft carrier, CVN-77, coincides with an apparent
DoN budget spike. As a percentage of the cost of the CVN being procured, this
spike is smaller than the FY1983 and FY1988 spikes.
As a percentage of the cost of the DoN budget, this spike at first
appears smaller than the FY1983 and FY1988 spikes, but is actually
somewhat larger than the FY1988 spike when the number of carriers procured
(2 in FY1988, as opposed to 1 in FY2001) is taken into account.
Table 7. Aircraft
carrier (CVN) procurement and
apparent
DoN budget spikes, FY1980-FY2001
(cost
figures in billions, rounded to nearest tenth)
|
FY |
No.
CVNs pro-cured |
Procurement
cost of CVN(s) |
Rough
apparent size of DoN budget spike |
Size
of spike expressed as percent of |
|
|
|
|
|
|
|
Then-year
$ |
Con-stant
FY01 $ |
Then-year
$ |
Con-stant
FY01 $ |
Proc.
cost of CVN(s) |
DoN
budget |
|
|
|
|
|
|
|
|
|
Total |
Per CVN |
|
80 |
1 |
$2.5 |
$4.7 |
no spike |
--- |
--- |
--- |
|
|
83 |
2 |
$6.9 |
$10.7 |
$6.0 |